The key milestones in the current forward programme for HS2 are:

Phase 1

Phase 2

Spring 2013

New blight scheme and safeguarding zone for Phase 1 in place

Consultation on the Exceptional Hardship Scheme for Phase 2

Consultation on Environmental Statement for Phase 1

Engagement programme on Phase 2 preferred route commences, to discuss local views and concerns

End of 2013

Introduce into Parliament a Hybrid Bill to provide necessary powers to construct and operate Phase 1 of the railway

Early 2014

Consultation on preferred route for Phase 2

Late 2014

Government announcement of the chose route for Phase 2

2015

Hybrid Bill for Phase 1 planned to receive Royal Assent, then preparatory works start

Commence engineering design, environmental impact assessment and preparation of Hybrid Bill for Phase 2

2017

Main Phase 1 construction works start

2026/27

Phase 1 opens to passengers

2032

Phase 2 opens to passengers